Overview of the year

REPOWER TAKES OVER 25 KM OF POWER LINES

More efficient grid operation in the Surselva

Share article

graphic
High-voltage twin cable line in the Surselva

In January 2020, Repower AG and Axpo Hydro Surselva AG finalised the takeover of around 25 kilometres of high-voltage twin cable line by Repower. Up to that point the two energy companies had each operated their own 60 kV grid systems in the Surselva. Combining the parallel grid structures makes operation and maintenance more efficient and economical. The takeover also cleared the way for the early dismantling of an overhead line in the municipality of LAAC to make way for an underground cable line.

https://onlinereport.repower.com/20/ar/en/wp-json/public/posts/

We use cookies to personalize content and ads and to analyze traffic to our website. You can find more information in the settings under privacy policy. By clicking “Accept all” you agree to the use of all cookies.You can find the full privacy policy here.