Overview of the year

Major project in Mendrisio on schedule

Handover of the first substation to AIM

Share article

graphic
New substation in Mendrisio (Canton Ticino)

The first substation in Mendrisio could be handed over to the client, AIM (Azienda Industriale Mendrisio), in September 2020. Repower has been commissioned by Swiss Federal Railways (SBB) and AIM on a general contractor basis to plan and build two turnkey substations. The contract, worth around CHF 20 million, is part of the NRLA (NEAT)/Alptransit New Railway Link through the Alps. Construction of the second substation (SBB) is scheduled for completion by the end of 2021.

https://onlinereport.repower.com/20/ar/en/wp-json/public/posts/

We use cookies to personalize content and ads and to analyze traffic to our website. You can find more information in the settings under privacy policy. By clicking “Accept all” you agree to the use of all cookies.You can find the full privacy policy here.